Radioactive Waste Management Advisory Committee (logo/home page)

Document Navigation:
Up - section index

 

RWMAC's Advice to Ministers on the Radioactive Waste Implications of Reprocessing

5. SOLID MATERIALS

5.1 Amounts of spent nuclear fuel to be reprocessed

The amounts of spent fuel that BNFL estimate would need to be reprocessed from 1 April 2000 onwards under each of the scenarios set out in Table 1 are given in Table 3.

It subsequently became clear that there were some differences in the information provided by BNFL to RWMAC and numbers appearing in the House of Commons Select Committee on Trade and Industry report on BNFL6 published in May 2000. The differences were primarily in THORP post-baseload figures. These differences were drawn to the attention of BNFL, who confirmed the numbers given to RWMAC were the correct figures from their viewpoint. They added that they had not supplied the figures quoted by the Select Committee. RWMAC have therefore proceeded on the basis of the BNFL figures, but remain concerned that two such important studies have led to publication of apparently contradictory figures.

The working assumption used for the analysis reported subsequently here, which is considered by RWMAC to be sufficiently accurate for its purpose, is that all the reprocessing of UK spent fuel was of Magnox and AGR spent fuel (i.e. overlooking the SGHWR spent fuel) and all reprocessing of overseas spent fuel was of LWR spent fuel (i.e. overlooking the Magnox spent fuel from Tokai Mura).

There are also 4,100 tHM of forecast UK spent fuel arisings that are not included in any of the scenarios considered. This is made up of about 1,200 tHM of Sizewell B LWR fuel (for which there are currently no plans for reprocessing) and 2,900 tHM of AGR fuel. The 2,900 tHM of AGR fuel are beyond the THORP "Extended" scenario and could potentially be treated in a number of ways. BNFL indicated to RWMAC that this could include reprocessing in a third decade of THORP reprocessing if there proved to be sufficient work to sustain plant operation for this long. (Note that this figure of 4,100 tHM for Sizewell B and AGR fuel beyond the scenarios considered of is an update of an earlier figure of 3,300 tHM given in reference 9).

In order to simplify the analysis, it has been assumed that the conditioning and direct disposal of spent fuel would not give rise to any secondary waste forms. In practice, however, the amounts of secondary wastes would not be negligible. For the purpose of this report, RWMAC has not attempted an analysis of the implications of spent fuel conditioning and disposal, other than to note the comparison in volumes of material arisings.

Table 3

Amounts of fuel to reprocessed from 1 April 2000 by scenario expressed in terms of tonnes of heavy metal, tHM

(Source: BNFL)

a) Magnox (uranium metal fuel)

Scenario

Fuel to be reprocessed

(tHM)

Of which at 1 April 2000

Irradiated fuel

(tHM)

To be loaded

(tHM)

M1: Extended

18,000

7,700

10,300

M2: Reference

10,500

7,700

2,800

M3: Existing fuel

7,700

7,700

0

M4: Stop Now

0

N/A

N/A


Notes to Table 3(a):

  1. For Magnox fuel, the weight of the heavy metal will approximate to the weight of the uranium metal in the fuel but excludes the cladding and other metal components.
  2. Approximately 40,000 tHM of Magnox fuel has been reprocessed before 1 April 2000.
  3. The 7,700 tHM already irradiated is all UK-owned, except for 250 tHM from Tokai Mura in Japan.
  4. The revised BNFL Magnox business plan discussed in section 4.2 will require 12,000 tHM to be reprocessed i.e. 1,500 tHM more than the reference scenario in the above table.

b) THORP (uranium oxide fuel)

Scenario

UK fuel (tHM)

Overseas fuel (tHM)

Overall total (tHM)

Irradiated fuel

To be loaded

Total UK

T1: Extended

3,900

500

4,400

16,300

20,700

T2: Reference

3,900

500

4,400

5,200

9,600

T3: Existing Contracts

3,900

500

4,400

3,600

8,000

T4: Baseload

1,000

0

1,000

3,200

4,200

T5: Stop Now

0

0

0

0

0


Notes to Table 3(b):

  1. For oxide fuel, the weight of heavy metal in the fuel will be about 20 per cent less than the actual weight of oxide fuel, and this excludes the clad, grids, and other metal or graphite components.

  2. AGR total includes 53 tHM WAGR fuel owned by UKAEA.

  3. LWR totals include 103 tHM from the UKAEA’s Steam Generating Heavy Water Reactor (SGHWR).

  4. THORP reprocessing before 1 April 2000 was 2,800 tHM, comprising 1,200 tHM AGR and 1,600 tHM LWR.

  5. This implies that completion of existing contracts will be equivalent to total reprocessing of 10,800 tHM through THORP.

  6. There are 1,200 tHM of Sizewell fuel and 2,900 tHM of long-term stored AGR fuel not included in the table figures: see section 5.1 of main text.

5.2 Rates of material arisings per tonne of spent fuel heavy metal reprocessed

The reprocessing of spent nuclear fuel gives rise to HLW, ILW, LLW reprocessed uranium and separated plutonium. Reprocessed uranium and separated plutonium are produced and stored in an oxide form, and so will be designated as RepUO3 and SepPuO2 from hereon, (where UO3 and PuO2 are the appropriate chemical formulae for the uranium and plutonium oxides produced).

The figures for amounts of materials arising from the reprocessing of one tHM of spent nuclear fuel are given in Table 4. These are based on information provided by BNFL at RWMAC’s request. The figures for HLW, and ILW were used in the analysis reported by BNFL’s stakeholder Waste Working Group9.

The HLW from reprocessing is first produced in a highly radioactive liquid (HAL) form. It is subsequently transformed into a solid vitrified form in the Waste Vitrification Plant at Sellafield (more is said of this in section 6.2). The volume figures quoted in Table 4 are for the vitrified form of the waste, and are therefore designated as VHLW. Any spent fuel which is not reprocessed, and for which no future use is foreseen, would also, in practice, need to be regarded as another form of HLW.

Materials generation rates may be expressed in various ways e.g. volumes, weight or, potentially, activity. However this is done, the results arrived at are usually required as a means of indicating the potential management requirements and costs associated with the materials. In reality, these management requirements and costs may depend in differing ways on the particular characteristics of the material concerned. For example, whereas volume may be the primary consideration in contemplating the storage and/or disposal of LLW, heat generation will be important in the case of HLW. RWMAC has presented its own results in a manner that it sees to be appropriate for this study. However, the Committee warns that, for the above reasons, simply adding weights or volumes across various types of material, a practice that has sometimes been adopted in the past, does not necessarily give a good indicator of the overall difficulty of dealing with that particular combination of materials. In reality, the specific requirements for each type of material need to be evaluated separately.

Table 4

Rates of materials arisings from reprocessing of one tonne of spent nuclear fuel heavy metal, tHM (Source: BNFL)

Fuel type

Material produced from reprocessing of one tonne of spent fuel heavy metal (tHM)

VHLW

(m3)

ILW

(m3)

LLW

(m3)

RepUO3

(t)

SepPuO2

(t)

Magnox

0.02

1.2

3

1.17

0.003

AGR

0.08

0.8

3

1.21

0.005

LWR

0.08

0.8

3

1.21

0.011

Notes to Table 4:

  1. All rates of arisings are for the standard packaging as discussed in Annex 6.
  2. Rates of arising of VHLW, RepUO3, and Sep PuO2 vary significantly with times in the reactor. All figures are averages. In general, they tend towards overestimation as opposed to underestimation.
  3. AGR fuel burn-up rates are lower than LWR burn-up rates. The rate of arising of 0.08 m3/tHM HLW is an average for the whole of THORP’s contracted business. Note, however, that a rate of 0.12m3/tHM is used for LWR in Scenario T1 (beyond the Reference scenario) to reflect the general trend to increasing reactor burn-up rates over time.
  4. The figure of 0.8m3/tHM for AGR reprocessing is based on future ILW arisings, minus the graphite and stainless steel grids and guide tubes which are removed from assemblies prior to pond storage.
  5. The LLW rate is an approximation, since a major part of LLW arisings are not directly related to reprocessing throughputs. The figure quoted of 3.0 m3/tHM is lower than that estimated by BNFL in the past14. This is due to major waste minimisation initiatives introduced at Sellafield in recent years, involving improved segregation, compaction etc15.
  6. Reprocessed uranium figures are for the oxide, UO3 (RepUO3). One t of UO3 equates to 0.83 t of U metal.
  7. Separated plutonium figures are for the oxide, PuO2 (SepPuO2). One t of PuO2 equates to 0.90 t of Pu metal.

5.3 Estimated material arisings per scenario

The figures given in Tables 3 and 4 have been used to estimate the various amounts of materials arisings for each of the scenarios considered. Table 5 below gives a summary of the solid materials predicted to be produced for each of the scenarios from 1 April 2000 onwards. The arisings are presented separately for the different Magnox and THORP scenarios. In practice, the way these arisings are treated and stored subsequently will be, to a degree, interdependent.

Table 5

Quantities of solid material arisings per scenario after 1 April 2000 (Source: BNFL, figures derived from Tables 3 and 4)

a) Magnox (uranium metal fuel) scenarios

Scenario

VHLW

(m3)

ILW

(m3)

LLW

(m3)

RepUO3

(t)

SepPuO2

(t)

Spent fuel

(tHM)

MI: Extended

360

21,600

54,000

21,000

54

-

M2: Reference

210

12,600

31,500

12,300

32

-

M3: Existing Fuel

150

9,200

23,100

9,000

23

-

M4: Stop Now

-

-

-

-

-

7,700

Notes to Table 5(a):

  1. RepU figures are for the oxide UO3. One t of UO3 equates to 0.83 t of U metal.
  2. SepPu figures are for the oxide PuO2. One t of PuO2 equates to 0.90 t of Pu metal.
  3. Spent fuel column shows UK Magnox spent fuel that would be left unreprocessed. In

practice, this would constitute another form of HLW.

b) THORP (uranium oxide fuel) scenarios

total amounts produced in the UK

Scenario

VHLW

(m3)

ILW

(m3)

LLW

(m3)

RepUO3

(t)

SepPuO2

(t)

Spent fuel

(tHM)

T1: Extended

2,100

16,600

62,100

25,000

201

-

T2: Reference

770

7,700

28,800

11,600

79

-

T3: Existing Contracts

640

6,400

24,000

9,700

62

-

T4: Baseload

340

3,400

12,600

5,100

40

3,400

T5: Stop Now

0

0

0

0

0

4,400

amounts remaining in UK after return of products from reprocessing overseas spent fuel with no substitution

Scenario

VHLW

(m3)

ILW

(m3)

LLW

(m3)

RepUO3

(t)

SepPuO2

(t)

Spent fuel

(tHM)

T1: Extended

400

4,300

62,100

5,300

22

-

T2: Reference

400

4,300

28,800

5,300

22

-

T3: Existing Contracts

400

4,300

24,000

5,300

22

-

T4: Baseload

130

1,500

12,600

1,200

5

3,400

T5: Stop Now

0

0

0

0

0

4,400

amounts remaining in UK after return of products from reprocessing overseas spent fuel with substitution

Scenario

VHLW

(m3)

ILW

(m3)

LLW

(m3)

RepUO3

(t)

SepPuO2

(t)

Spent fuel

(tHM)

T1: Extended

150

16,600

62,100

5,300

22

-

T2: Reference

350

7,700

28,800

5,300

22

-

T3: Existing Contracts

370

6,400

24,000

5,300

22

-

T4: Baseload

100

3,400

12,600

1,200

5

3,400

T5: Stop Now

0

0

0

0

0

4,400


Notes to Table 5(b):

  1. RepU figures are for the oxide UO3. One t of UO3 equates to 0.83 t of U metal.

  2. SepPu figures are for the oxide PuO2. One t of PuO2 equates to 0.90 t of Pu metal.

  3. Spent fuel column shows AGR spent fuel that would be left unreprocessed in addition to the 2,900 tHM, of AGR fuel discussed in section 5.1 that is not committed to reprocessing under any of the scenarios considered. In practice, this remaining spent fuel would need to be regarded as another form of HLW. The volume equivalence of unreprocessed spent fuel is discussed in the section 5.3 text.

  4. The table also does not include 1,200 tHM Sizewell B spent fuel (see section 5.1).

For the THORP scenarios, the three figures given are for : (i) amounts of material to be produced from reprocessing from April 2000 onwards; (ii) the amounts of that material remaining in UK after products from reprocessing of overseas spent fuel have been returned with no substitution; and (iii) the amounts of that material remaining in the UK after products from reprocessing overseas spent fuel have been returned with substitution allowed (see section 2.2 for an explanation of the meaning of substitution). In deriving the figures allowance has been made for the fact that there are early reprocessing contracts covering 1,500 tHM of overseas LWR spent fuel that did not include return of waste clauses.

The substitution calculations applied assume the return of additional HLW in return for ILW being left within the UK. For the purpose of the Table 5(b) analysis it is assumed that all the LLW generated by THORP reprocessing will remain in the UK, because of the availability of the Drigg LLW disposal facility. In practice, any effect on the amount of HLW returned overseas will be effectively negligible due to the relative activities of HLW and LLW.

Table 5 shows that the scenarios involving an early end to reprocessing also lead to an increase in the amount of unreprocessed spent fuel that would need to be managed as an additional form of HLW. RWMAC has concluded that all committed Magnox fuel will need to be reprocessed (see section 4.2). For the AGR spent fuel recorded in the table, RWMAC analyses have suggested that, the volume: weight equivalence would range between 0.4 m3/tHM (dismantled pins, wet storage) and 1.1 m3/tHM (stored as elements, dry). Conditioning for disposal would be expected to increase volumes at least from the minimum quoted above. For LWR spent fuel, the volume: weight equivalence would be about 0.4 m3 /tHM for storage as elements, with conditioning for disposal increasing volumes to between 0.9 and 1.5 m3/tHM.

Given that one tHM of AGR and LWR spent fuel are equivalent to about 0.08m3 of VHLW – see Table 4 – it may be said that reprocessing reduces the total volume of HLW to be dealt with

5.4 Combined scenario arisings in the context of total UK radioactive waste generation

Table 6 has used the figures given in Table 5 to estimate the total materials arisings from reprocessing for the various combined scenarios discussed in Section 4.2 – Combined Early Termination, Combined Reference and Combined Extended. Figures are given for (i) substitution not allowed and (ii) with substitution allowed.

Table 6

Future UK product arisings for various combined Magnox and THORP scenarios (Source: BNFL figures derived from Table 5)

no substitution

Scenario

VHLW

(m3)

ILW

(m3)

LLW

(m3)

RepUO3

(t)

SepPuO2

(t)

Spent fuel

(tHM)

C1: Combined Extended, M1 + T1

760

25,900

116,000

26,300

76

-

C2: Combined Reference, M2 + T2

610

16,900

60,300

17,600

54

-

C3: Combined Early Termination, M3 + T3

150

9,200

23,100

9,000

23

4,400

substitution

Scenario

VHLW

(m3)

ILW

(m3)

LLW

(m3)

RepUO3

(t)

SepPuO2

(t)

Spent fuel

(tHM)

C1: Combined Extended, M1 + T1

510

38,200

116,100

26,300

76

-

C2: Combined Reference, M2 + T2

560

20,300

60,300

17,600

54

-

C3: Combined Early Termination, M3 + T5

150

9,200

23,100

9,000

23

4,400


Notes to Table 6:
  1. RepU figures are for the oxide UO3. One t of UO3 equates to 0.83 t of U metal.
  2. SepPu figures are for the oxide PuO2. One t of PuO2 equates to 0.90 t of Pu metal.
  3. Spent fuel column shows AGR spent fuel that would be left unreprocessed as HLW. In practice, this would constitute another form of HLW. The volume equivalence of this is discussed in the section 5.3 text. This will be in addition to the 4,100 tHM spent fuel – 2,900 tHM AGR fuel and 1,200 tHM Sizewell B fuel – that will not be reprocessed under any of the scenarios considered (see section 5.1).

These estimates, of the total amounts of materials to be produced from future reprocessing, need to be set within the context of the amounts already held and the amounts eventually forecast to be generated by the current UK nuclear programme. This can be done using the outcome of the most recent UK Radioactive Waste Management Inventory13 and the latest annual estimates of civil plutonium and uranium stock figures published in the Department of Trade and Industry (DTI)16. The 1998 study by the Royal Society of the Management of Separated Plutonium4 also provides relevant background material. The Inventory information was based on a scenario equivalent to the RWMAC study’s Combined Reference scenario. The outcome of this analysis is set out in Table 7.

It must be emphasised that the current holdings and forecast total waste arisings given in Table 7 for the current UK nuclear programme are only estimates. This is because they are based on 1998 UK Radioactive Waste Inventory13 and 1999 DTI civil uranium and plutonium holdings16 figures which have been broadly estimated forward to 1 April 2000. Also some allowance has had to be made for the future return of overseas-owned reprocessing products which is not allowed for in the Inventory data.

Taking the various materials in turn, Table 7 shows that decisions on the future reprocessing of UK spent fuel are liable to have a marked impact on the amount of VHLW held by the UK in future. This is because VHLW comes almost exclusively from reprocessing. Current stocks of UK-owned VHLW of about 720m3 would be increased by between about 20 and 105 per cent depending on the extent of future reprocessing. This VHLW is produced initially as HAL which has to be processed through Sellafield’s Waste Vitrification Plant (see section 6.2).

Table 7 also shows that the Combined Early Termination scenario leads to an increase in the amount of unreprocessed spent AGR fuel that would need to be classified and managed as an additional form of HLW. The 4,400 tHM shown in Table 7 would be in addition to the 4,100 tHM – 2,900 tHM AGR fuel and 1,200 tHM Sizewell B fuel - not committed to reprocessing (see section 5.1). The volume: weight ratios given in section 5.3 indicate that this additional 4,400 would be equivalent to between 1,760 m3 (if wet stored, dismantled) and 4,840m3 (if dry stored as elements).

Table 7

Predicted UK-owned reprocessing conditioned materials arisings against current and forecast holdings


VHLW
(m3)
ILW
(m3)
LLW
(m3)
RepUO3
(t)
SepPuO2
(t)
Spent fuel
(tHM)
1. Estimated holdings
at 1.4.2000
720 77,000 6,000 90,000 61 N/A
2. Combined Extended
scenario arisings
760 25,900 116,100 26,300 76 -
3. Combined Reference
scenario arisings
610
(640)
16,900
(18,700)
60,300
(64,800)
17,600
(19,400)
54
(58)
-
-
4. Combined Early Termination
scenario arisings
150 9,200 23,100 9,000 23 4,400
5. Total waste arisings forecast for
current UK nuclear programme
1,345
(1,375)
209,000
(211,000)
1,900,000
(1,900,000)
108,000
(110,000)
115
(119)
N/A

Notes to Table 7:

  1. Row 1. VHLW figure provided by BNFL. ILW and LLW are derived from conditioned waste estimates given in the 1998 UK Radioactive Waste Inventory13. Two adjustments have been made to the ILW figure: (a) an upward adjustment of 5 per cent13 to the HLW and ILW quantities to allow for increasing generation between April 1998 and April 2000; (b) a downward adjustment to allow for the eventual return of products from the reprocessing of overseas LWR fuel reprocessed prior to April 2000. The LLW figure has been left unchanged, due to opportunity for disposal to Drigg. Reprocessed uranium and separated plutonium figures taken from published Department of Trade and Industry (DTI) data16.
  2. Row 2. Figures taken from Table 6, without substitution.
  3. Row 3. Ditto. Note that the figures in brackets allow for the additional 1,500 tHM of Magnox spent fuel to be reprocessed under BNFL’s revised Magnox business plan (see section 4.2 of the report).
  4. Row 4. Ditto.
  5. Row 5. Taken from 1998 UK Radioactive Waste Inventory13, which equates broadly to Combined Reference Scenario. The figure of 1,887 m3 of VHLW given in the Inventory has been adjusted by the 520 m3 which BNFL estimate will be returned to overseas customers and the 22 m3 held at UKAEA Dounreay. The 1998 UK Radioactive Waste Inventory figures for ILW and LLW have been left unchanged, although predictions of total forecast waste arisings actually fell between the 1994 and 1998 Inventories13 due to more efficient waste processing. However, adjustments have been made to allow for the eventual return of overseas materials. Figures in brackets again allow for additional generation as a result of BNFL’s revised Magnox business plan.
  6. The spent fuel figures are exclusive of the 4,100 tHM fuel – 2,900 tHM AGR and 1,200 tHM Sizewell B – that will not be reprocessed under any of the scenarios considered (see section 5.1).

Effects on the generation of ILW are less marked and on LLW less marked still. Future reprocessing would add between about 10 and 35 per cent of currently held UK stocks of ILW and between about 5 and 10 per cent of total forecast arisings. Future LLW arisings from reprocessing would be at most of the order of 10 per cent of arisings to date and no more than 5 per cent of the total LLW that will eventually either have been disposed of or held. This is because substantial amounts of ILW and LLW also arise from activities other than reprocessing e.g. day-to-day nuclear power generation, decommissioning etc. Increased LLW generation places additional pressure on the Drigg disposal facility.

As is the case with VHLW, reprocessed uranium and separated plutonium come solely from reprocessing. Thus, reprocessing of UK spent fuel continues to have a marked effect on the amounts of these materials held and owned by the UK. Table 7 shows that current holdings of uranium could be increased by up to about 30 per cent and current plutonium holdings could be more than doubled by the Combined Extended scenario.

Thus, whilst the effects of the different reprocessing scenarios on the amounts of ILW and LLW held are not large in percentage terms, there will be substantial impacts on the relative amounts of VHLW, spent fuel, reprocessed uranium and separated plutonium that need to be managed.

5.5 Materials arisings and other implications of the reprocessing of overseas spent fuel

The figures set out in Table 7 refer to the materials arising from the reprocessing of UK spent fuel, i.e. materials which are UK-owned.

Future Magnox reprocessing will apply solely to UK spent fuel, with the exception of the 250 tHM of fuel from Tokai Mura in Japan. However, a large proportion of THORP work consists of commercial reprocessing of overseas spent fuel.

On the one hand it may be seen to be potentially possible to set aside consideration of the reprocessing of overseas-spent fuel in contemplating the longer-term implications for the UK. This is on the grounds that the reprocessing products will be returned (although as section 5.3 has indicated, this does not apply to some 1,500 tHM of spent fuel covered by some early THORP reprocessing contracts). On the other hand, such reprocessing gives rise to discharges, needs for the interim handling of materials and, potentially, shifts in the balance of wastes remaining in the UK if substitution (see section 2.2) is allowed, all of which need to be suitably weighed against any commercial profit. In addition, it needs to be borne in mind that little, if any of the products of the reprocessing of overseas fuel, have actually been returned to date. Thus the timing issue comes into play.

RWMAC recommends that, in future, there should be greater transparency concerning holdings of overseas material within the UK and the proposed schedule for, and progress made towards, their return. Policy set out in the Cm2919 White Paper3 is that "the wastes resulting from foreign spent fuel should be returned to the country of origin, and the HLW should be returned as soon as practicable after its vitirification". In this context, also, RWMAC notes that the UK Radioactive Waste Inventory13 does not distinguish between future arisings that are covered by return clauses and those that must continue to be held within the UK, either because they are UK-owned or were not the subject of contractual return provisions. The Committee recommends that this be rectified in future Inventories.

[ ] [ Contents ] [ ]


  Page published 14 November 2000; last modified 3 January, 2003