ANNEX 7
THE ATOMIC WEAPONS PROGRAMME
History
1. The Aldermaston site was established in 1950, forming part of the
United Kingdom Atomic Energy Authority (UKAEA) until 1973, when ownership
and management control of the site was transferred to MoD. The Burghfield
site was originally established as a Royal Ordnance Factory for the manufacture
of munitions and later became part of the Atomic Weapons Establishment
(AWE) in 1987.
2. Following difficulties in commissioning Trident manufacturing facilities
at AWE, the Government decided to introduce modern management practices
at Aldermaston and Burghfield. The Atomic Weapons Establishment Act 1991
made provision for contractorisation of the sites and a Government-Owned
Contractor-Operated (GOCO) fixed term contract was let to Hunting-BRAE
Limited in 1993. Under the contract, Hunting-BRAE was made responsible
for management of all work activities at AWE. A holding company, AWE plc,
employed all staff at the AWE sites below Board level. MoD retained ownership
of the sites, all plant and equipment, and radioactive materials and wastes.
3. The Hunting-BRAE contract ran for seven years. Following publication
of the Strategic Defence Review in September 1998, the Secretary of State
for Defence announced that he had reviewed the options for the management
of Aldermaston and Burghfield to take effect after Hunting-BRAE's contract
expired in March 2000 and had decided that the sites would continue to
operate in the private sector under the general GOCO arrangements described
above.
4. Following a commercial tender competition held by MoD, the Secretary
of State announced (December 1999) that he had selected a new contractor,
AWE Management Limited (AWEML), a consortium of Serco plc, British Nuclear
Fuels plc and the Lockheed Martin Corporation, to operate the sites. AWEML
owns all the shares of AWE plc except for a "golden share" owned
by the Secretary of State.
5. As well as the main sites of Aldermaston and Burghfield, the AWE management
contract covers two other sites: Cardiff, where the site facilities are
being demolished and a contract to clean-up non-severe radioactive contamination
(depleted uranium and beryllium) will be let, and Blacknest, a seismic
and air monitoring station, which is outside the remit of this report.
6. The implications of these developments for this latest RWMAC review
of defence wastes are that, for most of the period covered, AWE was run
by a management contractor, Hunting-BRAE, which is now no longer in place.
At the time of preparation of this report (February 2001), the new management
contractor, AWEML, had been in place for less than a year. The conclusions
drawn by the Committee inevitably take account of these circumstances.
Changes in site regulation
7. Prior to commencement of the Hunting-BRAE contract on 1 April 1993,
the AWE sites were operated directly by MoD and the provisions of RSA93
did not apply. EA issued Letters of Agreement for the disposal of radioactive
wastes under the pseudo-RSA93 arrangements.
8. Contractorisation of the nuclear weapons programme brought the AWE
sites within the ambit of RSA93 and made them subject to independent regulation
by EA. The Agency now regulates the disposal of radioactive wastes, including
discharges, by the granting of RSA93 authorisations. The authorisations
set limits and conditions on disposals with which the contractor must
legally comply.
9. The second aspect of civil regulation that has come to apply to AWE
operations is the licensing of site operations by the Health and Safety
Executive (HSE; the Executive's responsibilities are actually undertaken
by NII) under NIA65. In the past, AWE held Crown Immunity from the provisions
of the Act and nuclear activities were subject to review by MoD's Assistant
Chief Scientific Adviser (Nuclear).
10. In May 1993, HSE announced that it was to carry out an extensive
review of safety at the AWE sites. This review culminated in a HSE report
published in October 1994. The report made 64 recommendations for improvement,
one of which was that the Secretary of State for Defence should remove
AWE's immunity from the provisions of NIA65. This was the position at
the time of RWMAC's last visit in January 1995. The sites were granted
nuclear licenses on 1 July 1997, once all but one of the HSE's recommendations
(which related to provision for waste storage) had been satisfactorily
addressed. NII now regulates nuclear operations at the sites, including
the accumulation and storage of radioactive wastes.
11. Thus, at the present time, AWE operation falls under the scope of
civil regulation under RSA93 and NIA65.
Transfer of the management contract
12. The intention to appoint AWEML as site management contractor meant
that the NIA65 site licence and the RSA93 disposal authorisations, both
of which were in the name of Hunting-BRAE, would effectively lapse. Neither
the license nor the authorisations could simply be transferred to a new
entity. In both cases, MoD decided, prior to any management contract changeover,
that the license and the authorisations should for the future, subject
to the views of the regulators, reside in AWE plc, in order to provide
for continuity of holding. This reflected the potential difficulty that
if, for some reason, AWEML ceased to exist, or was removed by the Secretary
of State for Defence (as the contract allows him to do), there would no
longer be a site licensee or RSA93 authorisee and that many of the activities
of the sites would, as a consequence, be no longer subject to civil regulation.
13. Action to license AWE plc, and to grant the authorisations, commenced
well before the transfer of the actual management contract. AWE plc submitted
applications to dispose of wastes under RSA93 in February 1998. Following
public consultation, EA subsequently decided to grant a new RSA93 authorisation
to AWE plc in March 2000.
14. NII informed the management contract tendering process, by giving
presentations and considering draft safety management prospectuses. However,
the main focus of the NII's action during this period was to ensure that
AWE plc was potentially licensable. New NIA65 licences were granted to
AWE plc on 1 April 2000, with provision for formal reviews of safety performance
after three and 12 months.
15. Subsequently a judicial review challenge to the granting of the new
RSA93 authorisations was launched by a local resident and the Nuclear
Awareness Group (NAG). The challenge was made on the following broad areas
of argument - that (as NAG and the local resident believed to be necessary
under the Euratom Treaty) the practice of manufacturing nuclear weapons
had not been justified; that such activities are a breach of international
law; that EA had acted unlawfully in failing to consult the Minister of
Health at the proper time; that the authorisations were issued prior to
Ministers' decision on "call-in" of the AWE application; and
that EA had acted unlawfully in not reconsidering the authorisations because
of the failure in the process.
16. The case was heard in January 2001. Judgement was given on 29 March
2001; the Judge did not find for the Plaintiffs on any of these grounds.
Key issues at AWE
17. RWMAC Members visited the AWE Aldermaston site on 16 and 17 February
2000 to receive presentations from the departing management contractor,
Hunting-BRAE, and from AWE plc staff. Visits to key site facilities took
place. The RWMAC group also met members of NAG. Subsequently, there were
meetings with AWEML, in May 2000, and with MoD's Nuclear Weapons Integrated
Project Team (NWIPT), in January 2001.
18. A number of core issues relating to the operation of the AWE sites
were discussed. These included site waste management practices and waste
management plans and strategies, facility management of waste arisings,
both solid wastes and environmental discharges (including operation of
the Pangbourne pipeline), ground contamination, liaison with the local
community and management of the transition from Hunting-BRAE to AWEML.
More will be said on each of these matters before comment is offered.
Waste management practices and documentation
19. Civil nuclear site licensing under NIA65 has, by its very nature,
imposed demanding requirements on AWE practices and their documentation,
including those relating to radioactive waste management.
20. In the period before the nuclear site licences were granted for Aldermaston
and Burghfield, Hunting-BRAE Ltd was required by HSE to devote considerable
effort to developing well thought out and comprehensive arrangements which
would satisfy the requirements of the site licences. These arrangements
have continued to be subject to critical review by NII and by the licensee,
and have been developed and improved upon. Arrangements for ensuring compliance
with the conditions of the site licenses are fully integrated into the
AWE Safety Management System as part of its quality assurance system.
All this documentation has been made available to the AWE workforce in
an easily accessible form, being published on the site Intranet and distributed
on CD-ROM.
21. Hunting-BRAE prepared safety cases for all major facilities on both
sites with a total of 80 such cases submitted to NII. The safety cases
were examined in accordance with a strategy developed at the commencement
of the licensing process by the NII site inspection team. In line with
the approach taken with other licensees, NII discussed, with the licence
applicant, the matters to be addressed in safety cases and the principal
methods used in the safety assessment process. All the nuclear, and the
majority of other, facilities which pose significant hazards at Aldermaston
and Burghfield now have safety cases covering their operation. There is
now also an AWE Nuclear Safety Committee (NSC) to peer review, and advise
on, management of safety at the sites.
22. Before it was replaced by AWEML, Hunting-BRAE had also prepared forward-looking
strategies and plans for radioactive waste management and decommissioning.
For both areas, the strategy set out policy principles and the plan then
identified the detail of the work to be carried out.
23. The radioactive waste management strategy cited principles of waste
minimisation at source, safe management and minimising disposal of waste
to the environment. The radioactive waste management plan, which was a
requirement of the AWE management contract and revised annually, set outputs
for work to be carried out in the context of volumes of waste arisings
over a 10 year period.
24. The decommissioning strategy was aimed at the decommissioning of
redundant facilities to a timescale which was as early as was practical,
encompassing rehabilitation and reuse where possible, and placement of
facilities scheduled for decommissioning on a defined "care and maintenance"
regime. The subordinate decommissioning plan provided a prioritised 10
year decommissioning programme as well as providing indicative timeframes
(up to 55 years) for decommissioning of all site facilities and estimates
of waste arisings. This decommissioning plan was also revised annually
and issued to NII.
25. The Committee was not able to analyse these strategies and plans
in detail but, on the face of it, they provided a sensible and apparently
robust basis for reviewing and documenting future work against changing
requirements. On taking over the AWE management contract, it was understandable
that AWEML wished to review the existing radioactive waste management
and decommissioning strategies in the context of its own proposals for
management of the sites.
26. As a first step, AWEML committed itself to continue with Hunting-BRAE's
strategies and plans until a review could be carried out. It is clear,
however, that the new company has different views, in some areas, to those
of its predecessor. Notably, it has produced an integrated radioactive
waste management and decommissioning plan. AWEML is also believed to be
seeking an extension of the management contract from 10 to 25 years to
allow a longer term perspective and the injection of additional private
sector funds. RWMAC understands that discussion of a possible contract
extension was underway with MoD at the time of preparation of this report.
27. At first sight, RWMAC has no difficulty with the concept of an extended
contract, and a greater degree of public-private partnership, provided
these changes are implemented in the right way. For example, the Committee
would not like to see a longer contract giving rise to longer timescales
being allowed for work, particularly decommissioning.
28. RWMAC was allowed sight of the draft combined waste management and
decommissioning plan prepared by AWEML.
29. The combined plan is pitched at a high level with relatively little
detail. Its main thrust is the "Five year vision" statement
for waste management and decommissioning at AWE, on which the Committee
offers the following comments :
- as a whole, the statement has been drawn up within a sensible framework
and its preparation is warmly welcomed;
- it is stated that the aim is for the lifetime cost of the decommissioning
programme to be quantified and optimised by regular review on a net
present value (NPV) basis. The NPV is not specified, however, and it
is not clear, therefore, how optimisation will be achieved. In particular,
the discount rate used in any NPV calculation is crucial to the viability
of any sensibly phased decommissioning plan. This has previously been
commented on by RWMAC in the context of its report on Dounreay4;
- there is welcome emphasis on hazard reduction through management
of ILW. However, it is clear that further decisions will be required,
as early as 2002, on planning for further ILW storage;
- the statement recognises the need for an improved liabilities estimation
process with a consistent approach for waste, and related cost, estimates.
Lack of data will, again, prejudice the chances of achieving optimisation
and the proposal to develop computer-based models to produce better
estimates is therefore welcomed.
30. The intention is stated to carry out an annual review of the overall
strategy and costs of waste management and decommissioning, incorporating
a comprehensive risk management strategy. This, again, is to be welcomed.
31. In all, the combined plan amounts, in RWMAC's view, to a credible
and thoughtful piece of work. Some interesting procedures are, in particular,
introduced, for example, discussion of AWE-specific waste specifications
(inter alia, to maximise the capacity of containers), and to introduce
hot-cutting techniques to speed-up decommissioning work and save worker
dose. The plan also proposes, once the structures have been decontaminated
and the radiological hazards removed, to establish "site decommissioning
zones" to maximise the opportunity for conventional dismantling and
optimise associated safety measures.
32. RWMAC believes that it is in the interests of both AWEML and MoD
for the plan to be finalised and made public as soon as is practically
possible. It would also be helpful if the ways in which the AWEML plan
differs from Hunting-BRAE's forward plans for the sites could also be
made clear.
33. During the course of its discussions with both Hunting-BRAE and AWEML,
RWMAC was given sight of two and ten year vision statements for AWE (in
addition to that for five years, now overtaken by the statement addressed
above), which the Committee understands were required as part of the new
contract management bidding process. The Committee feels that, in principle,
such vision statements can potentially provide a powerful means of communicating
to the public the progress that is intended to be made at a site such
as AWE, providing they are framed in language that is understandable by
the interested layperson.
Management of solid wastes
34. Radioactive waste streams from the AWE Aldermaston and Burghfield
sites include solid ILW and LLW. These wastes arise from the production,
servicing and decommissioning of nuclear warheads, research and development
of warhead technology, and decommissioning of redundant nuclear process
plant. Uranium, plutonium and tritium are the principal radionuclides
in the waste streams. Small quantities of wastes containing cobalt and
caesium are also produced from maintenance of AWE's HERALD research reactor,
which is non-operational and awaits decommissioning.
ILW
35. During its period of tenure, Hunting-BRAE initiated a review of ILW
storage on the Aldermaston site. This review is expected to be complete
in 2002. There are about 13,000 drums of ILW on site which are being checked
and, in some cases, repackaged. For the stores, aisle, as opposed to block,
stacking is now used so that every drum can be accessed and examined within
two hours. Of the 7,000 drums that had been checked at the time of the
RWMAC's visit in early 2000, only four had been found to defective and
the contents, therefore, to need repacking. In design terms, the life
of both packaging and stores is anticipated to be 25 years, but it may
be that their working life will prove to be longer.
36. The eventual aim is storage of ILW in Nirex-approved containers,
a process that requires its supercompaction. AWE's work to date has indicated
that of the 13,000 ILW drums, up to 4,000 may contain LLW suitable for
disposal to Drigg. At the time of the visit, RWMAC took the view that
this situation could have been prevented if measures had been in place
for better monitoring, segregation and sentencing of solid wastes. AWEML,
however, has indicated that some of the wastes were generated as early
as 1965 and that instrumentation, sufficiently sensitive to discriminate
between drums of LLW and ILW from a known fissile material environment,
has not, until now, been available.
37. AWE has completed a new ILW store at Aldermaston to hold the Nirex
containers which is expected to be in operation by the end of 2001, with
the first consignments of Nirex containers made around 2006. Space on
site has been earmarked for a further store if required (although the
building on which it currently stands will need to be demolished). Purchase
of a drum monitoring facility (including a high-resolution gamma spectrometer
and an active/passive neutron monitor), to address the problem of segregating
ILW and LLW, was originally recommended to MoD by Hunting-BRAE, but agreement
on its acquisition was not reached. The decision now rests solely with
AWEML. Space has also been allocated for the new facility.
38. A project to retrieve and immobilise radioactive waste sludges in
the old waste treatment complex (WTC) was also originally initiated by
Hunting-BRAE. Prior to the change of operating contractor, NII issued
a number of project specifications to control the accumulation of waste
to the sludge tanks. NII also specified the need for retrieval, conditioning,
and packaging of the wastes for their long-term site storage. One of the
first contracts placed by AWEML was for a feasibility study for the work
using a vitrification process. In parallel, a contract has also been placed
for the cementation of some of the sludges classified as LLW. Cementation
of all the LLW sludge from one of the tanks was completed in early 2001,
apparently well ahead of the schedule provided for in NII's specifications.
39. There is a review of ILW storage arrangements each year, the outcome
of which is fed into AWE radioactive waste management and decommissioning
plans. A study was carried out under contract to examine the scope of
the Letters of Comfort required from Nirex and the process for obtaining
them. In future all new projects will be assessed, among other things,
in terms of the Letter of Comfort requirements for associated waste arisings.
LLW
40. It is understood that NII has commented favourably on what has been
achieved at Aldermaston in recent years in the management of solid LLW,
particularly minimisation of arisings. The Head of Waste Management at
AWE interfaces with the waste minimisation officer in each building. Each
building has a waste service agreement. Workface staff are, thereby, encouraged
to think about what kinds and volumes of wastes they are producing. Low
force compaction is used to reduce the volume of waste placed into drums.
Vacuum packing, using pumps and HEPA filters, is also used for solid LLW,
and also for ILW.
41. There are various authorised routes for the disposal of solid LLW
from the Aldermaston site. These include direct disposal to Drigg, disposal
to Drigg after compaction at UKAEA Winfrith, and incineration of some
organic solid, and also liquid, wastes. There are special security controlled
arrangement for disposal of solid explosives and other munition wastes
contaminated with radioactivity.
42. LLW from other AWE sites is transferred to Aldermaston prior to disposal,
but only limited amounts of LLW need to be stored on an interim basis
before disposal.
43. RWMAC notes that AWEML has a Waste Management Forum to share best
practice among managers and operators. All in all, RWMAC's view is that
management of LLW is conducted to a good standard. Good progress has been
made, in particular, with waste minimisation.
Environmental discharges
44. AWE has not been as successful in reducing the volume of discharge
of liquid wastes from Aldermaston. This is due principally to the fact
that rain water and surface water ingress can carry radioactive contamination
into the site radioactive effluent treatment tanks, resulting in an increase
in the amount of effluent that needs to be managed. RWMAC understands
that AWEML has initiated a programme to tackle this problem. The initiative
derived from a BPEO study for the disposal of radioactive aqueous waste
that EA required should be undertaken as part of new authorisations granted
to AWE plc. Among other things, the existing piped network for the collection
of aqueous wastes will be progressively taken out of service and replaced
by tanker collection. Other changes in the way the collected waste is
treated are under active consideration.
45. Traditionally, liquid wastes containing uranium and plutonium produced
at AWE have been collected in holding tanks, sampled and pumped to a liquid
effluent treatment plant where they have been subject to a flocculation
process designed to trap the uranium and plutonium in solid form. These
wastes also contain tritium which is not removed. The treated liquid effluent
has then been discharged to the River Thames near Pangbourne through a
twin-pipe 18 kilometre-length dedicated bitumen-coated steel pipeline
("the Pangbourne Pipeline").
46. AWE has also been authorised to dispose of low activity tritium and
uranium effluent to the Silchester sewage treatment works, from where
it is eventually discharged to the Thames.
47. AWE has not, in the past, been authorised to dispose of any liquid
wastes to the Aldermaston Stream, a tributary of the River Kennet. However,
the presence of low levels of tritium in the stream has been known for
many years, and was assumed to have originated from ground deposition
of gaseous tritium discharged from the AWE stacks washed to the ground
in rainfall.
48. However, it was eventually recognised that tritium was actually being
discharged via the North Ponds Waste Management System introduced, in
October 1998, to collect run-off water from the northern part of the Aldermaston
site. The existence of tritium in surface waters at the north-west corner
of the site had also been known for many years, although this contamination
does not appear to have affected deeper-level drinking water sources.
In 1999, EA successfully prosecuted Hunting-BRAE for releasing tritium-contaminated
water from the North Ponds to the Aldermaston Stream without authorisation.
49. The revised authorisation issued by EA to AWE plc in March 2000 made
a number of significant changes to these liquid radioactive waste discharge
arrangements. The changes included a requirement for AWE to cease discharges
of radioactive wastes via the Pangbourne Pipeline within five years, and
to the Silchester sewage works within ten years. While authorising existing
radioactive waste discharges from the North Ponds to the Aldermaston Stream,
it required that these should be eliminated within five years.
50. To support these requirements on AWE, EA also set an objective that,
within five years, management of radioactive liquid effluents from plant
operations at AWE should employ a system that is BPEO, with a strong presumption
that it should be based upon evaporation technology. A time limit of six
months was set for delivery by AWE of a site-wide Liquid Effluent Management
Strategy and a BPEO study report. These documents were delivered and published
in September 2000. These studies did not consider the Pangbourne Pipeline
and, to that extent, it appeared to RWMAC that not all the environmental
options were actually considered as part of the EA proposal (formulated
no later than mid-1999) to close the pipeline.
51. RWMAC had commented (in its response of November 1999)5
on these EA requirements as they were set out in the Agency's public consultation
documents on the new AWE authorisations. The Committee had, in the past,
also noted problems with the Pangbourne Pipeline operation including the
risk of leaks and wash-out of plutonium and uranium scale into the Thames3.
52. The Committee's November 1999 response noted that a new treatment
process involving evaporator technology would not remove tritium, the
predominant radionuclide in the effluent, and would merely substitute
an airborne tritium discharge route for that of the liquids. It would,
however, remove other radionuclides such as plutonium and uranium. It
would, in addition, introduce a new waste stream in the form of sludges.
RWMAC also noted that the cost of replacing the pipeline with an evaporator
was, in terms of critical group dose saved, estimated to be £2 million
per microsievert, which appeared costly relative to the very low level
of public exposure.
53. RWMAC believes, however, that uncertainty concerning the condition
and operation of the Pangbourne Pipeline, and the need to alleviate understandable
public worry, are clearly important factors that also need to be taken
into account. Thus, whilst taking the view that the issues were relatively
finely balanced, the RWMAC response indicated that the Committee's main
concern was not with the proposed closure of the Pangbourne Pipeline per
se, but rather the transparency of the processes employed by EA to arrive
at the decision to require its closure. If the March 2000 EA decision
was taken only after a full systematic analysis had been carried out,
this was not apparent from the consultation documents. From the available
information, it is unclear whether the doses from proposed new schemes,
however minuscule, were adequately compared to the status quo of retaining
the pipeline. On the face of it, much more could have been done by EA
to demonstrate the need for transparency in the decision-making process.
Site contamination
54. As large industrial sites of long-standing, Aldermaston and Burghfield
suffer from a number of forms of ground contamination that need to be
dealt with. These include radioactive material.
55. In 1996, AWE initiated a land quality survey of the 670-acre Aldermaston
site. The survey was inevitably a major undertaking and included analysis
of water from streams, drains and boreholes. The initial findings of the
survey were published in 1997 in the form of a public information leaflet.
This highlighted a number of areas where organic solvents (trichloroethylene
and oils), mercury and radionuclides, including plutonium, had been found.
56. Since that date, more survey work has been carried out and there
have been further published updates. The extent and scope of the surveys
have been extended, including more off-site sampling. Some remediation
work has also been undertaken. To date, work has concentrated on areas
where contamination is thought to be most likely, but other areas will
also be covered in due course.
57. Use of tritium is an inherent feature of the manufacture and handling
of nuclear warheads. For many years tritium has been known to be present
in the ground and in surface waters at the north west corner of the Aldermaston
site, and measurements of concentrations have been published in annual
environment, safety and health reports.
58. While the radiological consequences of tritium are relatively low,
knowledge of its existence as an on-site contaminant, the fact that it
can run-off into watercourses and liquid waste management facilities around
the site, and its inclusion within the regulatory regime for Aldermaston
through authorisation of discharges from the North Ponds, all mean that
its presence has become the subject of increasing attention. To date,
it has proved impossible to identify the precise source(s) of the tritium
contamination. The latest EA authorisation document states that it should
be possible for AWE to carry out work to identify and remediate the source(s),
so that levels of tritium in the groundwater at Aldermaston can, in due
course, be returned to natural background values. Investigations by AWE
to identify the source or sources of tritium are continuing.
59. In addition to this work, RWMAC believes that the scope for carrying
out a full site-wide contaminated ground characterisation and remediation
programme should be considered by AWE in line with policies adopted at
other major nuclear sites.
60. In addition to AWE's land quality survey, Southampton University
has been commissioned to conduct a three year radiological study of the
Aldermaston and Burghfield sites. This essentially follows up a similar
investigation around Greenham Common carried out by the University on
behalf of West Berkshire District Council. At AWE, sampling is undertaken
in three phases, gradually spreading out from the immediate vicinity of
the two sites to a distance of more than 20 miles. Full independence of
the work is assured by a Scientific Information Group, comprising representatives
of local councils. The Group receives study data at regular intervals.
All results are published. By the middle of the third year of work, no
results of any radiological significance had been recorded.
Liaison with the local community
61. The previous management contractor, Hunting-BRAE, introduced a number
of initiatives to extend liaison between the company and the local communities
around the Aldermaston and Burghfield sites.
62. A Local Liaison Committee (LLC) was set up in October 1993. This
meets three times a year, with representatives of AWE's senior management
together with elected politicians and officers from neighbouring local
authorities attending. EA and NII also attend.
63. An extensive AWE Website has been set up. Details of safety performance
and environmental impact and an Annual Report are published. A community
newspaper goes to 18,000 households in the surrounding areas.
64. In 1997, the company sought to adopt an "open door" information
policy aimed at promoting the image of AWE as a good and safe neighbour
that wished to play a positive role in local community life. Local groups
were invited on site. Individual managers were expected to make themselves
available to the public and to account for AWE's performance and safety
record. A Community Committee was set up to co-ordinate support for local
community interests, charitable work and school science activities.
65. Responding to criticism from local pressure groups, notably the Nuclear
Awareness Group (NAG), that they cannot attend the LLC, Hunting-BRAE told
RWMAC that its aim was to improve relations with these groups. RWMAC was
informed that members of NAG had accepted an invitation to visit the Pangbourne
pipeline, and that company staff had spoken at NAG conferences and meetings.
NAG had also been given a presentation on contaminated land findings.
However, having spoken to NAG representatives at the time of its site
visit, it was unclear to RWMAC that this initiative has, as yet at least,
been particularly successful in improving relationships. Nevertheless,
RWMAC is supportive of all possible efforts maintains to open and maintain
dialogue between AWE and local interest groups on all issues of interest.
66. Initial signs are that AWEML is committed to maintaining and building
upon the improved public relations initiatives introduced by Hunting-BRAE.
It appears that the company has endeavoured to engage the LLC more and
has been looking to improve the quality of published information. It is
too early to assess the ultimate impact and value of such initiatives.
Site management transition
67. It is RWMAC's impression that, not least as a result of the application
of RSA93 and NIA65 regulatory procedures, there were substantial improvements
in the standard of radioactive waste management at AWE during the period
of Hunting-BRAE's management contract tenure. These have included the
preparation, documentation and application of safety management procedures;
formulation and documentation of waste management and decommissioning
strategies and plans; a start to the process of site contamination characterisation;
and more meaningful contacts with the local community.
68. There have also been some setbacks, a notable example being prosecution
by EA for the unauthorised discharge of tritium-contaminated water from
the North Ponds. There remains much for the incoming management contractor,
AWEML, to do. But, from its position as an external observer, RWMAC perceives
that, overall, the situation now is much better than it was prior to 1993.
69. The perception of others may, of course, be different if only because
the issue of nuclear weapons manufacture will always be controversial.
AWE's present management has also had to address a difficult legacy of
waste problems and site contamination from earlier days, when operational
standards were well below the levels of those considered acceptable, and
required by the regulators, today.
70. The onus is now on the new contractor, AWEML, to maintain and, hopefully,
elevate the rate of improvement and achievement in waste management. A
key instrument will be the way in which the new contract impacts on this,
and related, areas such as decommissioning and site environmental management.
71. Many of the new contract provisions are confidential and RWMAC has
not seen the document itself. It was reasonably clear to RWMAC from its
February 2000 site visit, and a subsequent meeting with AWEML three months
later, that the contract is markedly different from that with Hunting-BRAE.
Its declared aim is for AWEML to be able to "run the business"
of weapons manufacture, decommissioning, and research into new technology
without continual and frequent reference back to MoD.
72. The driver to change the arrangements derives from problems perceived
to be inherent in the Hunting-BRAE contract. These included the piecemeal
approach required as part of setting contractor deliverables, the need
for detailed price negotiation and MoD approval, and the limited extent
of risk transfer to the contractor. It was felt that the degree of MoD-contractor
interface inhibited long-term strategic planning. The solution was identified
in terms of a new style of contract that would provide a high incentive
for good performance, with the burden of risk placed on the contractor.
73. The contract tender competition was framed, inter alia, to reflect
these concerns. It seems logical to believe that the AWEML bid was chosen
because, in addition to proposing an attractive contract cost for the
core deliverables of weapons work, its proposals for the profit element
of the contract were also preferred on grounds of both the amount of money
involved (relative to the cost element) and contractor risk. In other
words, the amount of profit put at risk by the contractor (i.e., subject
to performance evaluation) was probably the highest in the case of the
AWEML bid.
74. The contract arrangements work as follows. AWEML draws down payment
for expenditure on the entire weapons programme on achievement of "payment
milestones" relating to weapons work and safety. Any underspend (which
might be deemed excessive profit) is shared between AWEML and MoD, and
can increase the contractor's profit. However, the profit element (which
is believed to be about 10 per cent of the contract bid) is paid subject
both to these milestones being achieved and to performance against "performance
measures" (for activities encompassing waste management, plant and
site decommissioning, and environmental management). The performance measures
dictate the greater level of draw-down against this profit element. (It
seems to RWMAC that it is expenditure incurred against the cost element
of the contract price that, in practice, probably determines most of the
company's overall net income.)
75. The contract can, therefore, work either to the company's advantage
or to its disadvantage, depending on performance. For example, achievement
of all milestones and performance measures would result in a significant
profit achievement. If, on the other hand, circumstances (such as responding
to regulatory intervention) meant that it could not achieve more than
a few performance measures, the profit would be small.
76. The milestones and performance measures are set each year by negotiation
between MoD's NWIPT and the contractor. They are not incorporated into
the contract, but the performance measures are consistent with the AWEML
combined waste management and decommissioning plan for AWE. So while the
measures are not themselves subject to approval by NII and EA, this combined
plan (in part a response to regulatory proposals for the site) is subject
to regulatory scrutiny.
77. It is clear that the first year of contract operation may be regarded
as a honeymoon period in terms of the setting of performance measures
- some, including those, for example, relating to the three and 12 month
regulatory reviews of AWEML (referred to in paragraph 14) being essentially
scene setting . The expectation is that the measures will be made more
stringent after March 2001. Nevertheless, RWMAC has been given a summary
of the milestones (35 in all) and the performance measures (about 70 in
total) agreed between AWEML and NWIPT for the first year of the contract.
Given that the first year represents, in effect, a period of acclimatisation,
the Committee believes that the performance measures point forward, in
a credible and realistic way, towards the development of appropriate incentives
for the management of radioactive waste at the sites.
78. NWIPT itself commented to RWMAC that, for 2000-2001, AWEML has achieved
all the payment milestones and is performing well against the performance
measures. It is notable, however, that the company has not yet achieved
the ISO14001 standard for site environmental management, but hopes now
to do so by December 2001.
RWMAC comment
79. RWMAC believes that since it last reported on AWE, in December 1997,
considerable progress has been made towards the effective management of
radioactive waste. A start has also been made towards the characterisation
of site contamination at Aldermaston. Nevertheless, there are a number
of key areas where problems remain to be addressed.
80. Much of the progress must be credited to the previous management
contractor, Hunting-BRAE. RWMAC also believes that the application of
civil site regulation - under RSA93 in 1993 and NIA65 in 1997 - has also
been a major factor.
81. The new management consortium, AWEML, has yet to prove itself in
concrete terms. It is, from RWMAC's perspective, too early for any certain
judgements to be made, but the Committee hopes that AWEML will be set
high standards in order to maintain and, hopefully, build upon, the improvements
in waste management already achieved. Application of the civil regulatory
requirements is bound to support this.
82. In RWMAC's view, the new contract arrangements do, in principle,
provide sufficient incentive for AWEML to achieve a high standard of management
of AWE wastes. There are, nonetheless, areas of uncertainty and potential
concern. The new contract is much less specific about how the contractor
should allocate and prioritise its use of resources. It must be remembered
that AWE's core business is nuclear weapons. And MoD's decision to refigure
the contract appears to have reflected reservations about the ability
of the previous arrangements to facilitate long-term strategic thinking
and to shift risk to the private sector, rather than the effectiveness
of waste management per se.
83. There is evidence from the past that original timescales for radioactive
waste management projects at AWE - both provision of stores and processing
facilities - have been allowed to slip. This may have been due to inadequate
provision of resources or to the process of negotiation between MoD and
the contractor.
84. Safeguards against project slippage exist, in principal, in the new
management arrangements (as part of provision for incentivisation). On
the face of it, the weighting given to environmental performance measures
could work well. Much depends on what measures are selected and how they
are applied. These arrangements will only really mature in coming years.
RWMAC's main doubt is that if AWEML finds itself with problems in its
core business, its focus on ancillary programmes may weaken. For all its
faults, the previous contract seems to have provided some mechanism for
maintaining the visibility of waste management and decommissioning, even
if these were not always effective in practice. But the Committee would
not wish to be prescriptive - it is simply too early to be clear. An additional
issue is that, in due course, MoD needs to consider whether the current
contract should be extended from 10 to 25 years, allowing the injection
of private investment facilitation of "spend to save" capital
schemes, including proposals for waste management and decommissioning.
85. It is understandable that, following its takeover of the AWE management
contract, AWEML wanted to review the radioactive waste management and
decommissioning plans formulated by Hunting-BRAE. However, with a year
almost gone since management contract takeover, it is, in RWMAC's view,
presentationally important for AWEML to finalise, in conjunction with
MoD and the regulators, and publicise its own radioactive waste management
and decommissioning plans, even if they are still subject to formal review,
in order to avoid giving the impression of procrastination. It is also
important that any differences from the Hunting-BRAE plans are highlighted
and explained.
86. During the last two years of its tenure, Hunting-BRAE initiated steps
to begin decommissioning of some of the older, and more contaminated,
manufacturing and waste management buildings at Aldermaston. These are
challenging tasks, involving, for example, large numbers of gloveboxes.
It is important that this initiative is maintained. The extent to which
the AWEML combined waste management and decommissioning plan is consistent
with Hunting-BRAE's annual plans and strategies is not certain. Attention,
both by MoD and the regulators, might be given to identifying any potential
problems in areas of ongoing work inherited by AWEML from Hunting-BRAE.
87. Significant progress has also been made towards improving the packaging
and storage of ILW at Aldermaston. AWE liaison with Nirex, which was the
subject of some criticism at the time of the last RWMAC visit in January
1995, has also been substantially improved. But this is, nevertheless,
an example of where the current lack of any Government policy for the
long-term management of radioactive waste is making life difficult for
operators. At present, waste is being repacked into containers and stores
with a 25-year life. A future project is to repackage the wastes in containers
that Nirex deem will ultimately be suitable for disposal. But not only
is there no clear Government policy on long-term radioactive waste management,
including the possibility of deep underground storage or disposal, the
current hiatus prevents effective consideration by regulators and operators
of timeframes (for example those for packaging and storage) and ancillary
issues such as conditioning and the passive safety of wastes.
88. For the moment, dealing with LLW at AWE appears to cause relatively
few problems, although the Committee notes that a large number of legacy
drums originally treated as ILW may, once new technology assay equipment
is available, be shown to be appropriate for disposal as LLW to Drigg.
89. A start has now been made with characterisation of ground contamination
of the AWE site. RWMAC accepts that this is a process that could, in theory,
consume significant resources very rapidly. Thus, while progress must
clearly continue, there is a need for a suitable balance to be achieved
with other waste management priorities. The Committee believes that the
issue of tritium could generate real problems. The March 2000 EA discharge
authorisation suggested that it would be possible for AWE to locate one,
or several, discrete sources that could then be remediated in order to
"reduce radioactive discharges from AWE to the River Thames to zero
when levels of tritium in groundwater at Aldermaston return to background
values". RWMAC does not share EA's optimism that this will be achievable
particularly if some of the tritium comes from rain washout of stack discharges.
Nor will the possible future use of evaporation technology remove tritium
from such discharges. With this in mind, the Committee has also questioned
the achievability of the objective of the Government's proposed UK Strategy
for Radioactive Discharges 2001-20202
that "by 2010 total beta/gamma discharges from nuclear weapons production
at AWE (including tritium) are expected to reduce to zero".
90. RWMAC notes that outstanding issues of the integrity and operation
of the Pangbourne Pipeline have now effectively been resolved by the decision
for its closure by 2005. The issues raised by this decision are set out
at an earlier point in this Annex. The major concerns, in RWMAC's view,
do not relate to the management of AWE liquid wastes per se, but to the
processes which EA adopted, or did not adopt, in arriving at its authorisation
decision. It was not clear to the Committee that the was based on a full
and appropriate technical analysis.
91. Nevertheless, closure of the pipeline and the introduction of alternative
technology to reduce discharges represent a major challenge for AWE over
the coming years. One issue that will need to be decided by AWML concerns
the future of the Radioactive Liquid Effluent Treatment Plant (RALETP)
which has not been taken into operation because of technical difficulties.
92. Lastly, RWMAC believes that AWEML must also maintain Hunting-BRAE's
commitment to maintaining good communication with the local community,
recognising that this may sometimes lead to difficulties that must be
overcome. The Committee strongly supports the need for openness and transparency
in radioactive waste management. The last RWMAC report concluded that
"AWE needed to take steps which would lead to greater public understanding
of its work, and public confidence in its management of radioactive materials".
Major progress has already been made towards meeting the needs of the
public and this must be maintained.
[ Previous ] [ Contents
] [ Next ]
|